January – March 2013 Programming/Schematic Design
February - March 2013 Issue RFP for Architectural Services and Construction Manager
Early March 2013 First FLC Renovation User Group meeting
Proposed Grand Reading Room. See more renovation images.
March 2013 Campus-wide Project Oversight Meeting
April - May 2013 Architect Interviews/Selection
June - August 2013 Schematic Design
October 2013 Schematic Design Oversight Committee Presentation
October 2013 – January 2014 Design Development
May – July 2014 Building Permit Review
April – May 2013 Construction Manager Interviews/Selection
July 2014 Contracts
August 2014 Construction begins
May 2016 Project completion